Section:- I All case are Complusory
Case 1
Disaster Recovery at Marshall Field’s (Another Chicago River Story)
Early in the morning
on April 13, 1992, basements in Chicago ’s
downtown central business district began to flood. A hole the size of an automobile
had developed between the river and an adjacent abandoned tunnel. The tunnel,
built in the early 1900s for transporting coal, runs throughout the downtown
area. When the tunnel flooded, so did the basements connected to it, some 272
in all, including that of major retailer Marshall Field’s.
The
problem was first noted at 5:30 A.M. by a member of the Marshall Field’s
trouble desk who saw water pouring into the basement. The manager of
maintenance was notified and immediately took charge. His first actions were to
contact the Chicago Fire and Water Departments, and Marshall Field’s parent
company, Dayton Hudson in Minneapolis .
Electricity—and with it all elevator, computer, communication, and security
services for the 15-story building—would soon be lost. The building was
evacuated and elevators were moved above basement levels. A command post was
quickly established and a team formed from various departments such as
facilities, security, human resources, public relations, and financial, legal,
insurance, and support services. Later that day, members of Dayton Hudson’s
risk management group arrived from Minneapolis
to take over coordinating the team’s efforts. The team initially met twice a
week to evaluate progress as the store recovered. The goal of the team was to
ensure the safety of employees and customers, minimize flood damage, and resume
normal operations as soon as possible. The team hoped to open the store to
customers 1 week after the flood began.
An
attempt was made to pump out the water; however, as long as the tunnel hole
remained unrepaired, the Chicago River continued to pour into the basements.
Thus, the basements remained flooded until the tunnel was sealed and the Army
Corps of Engineers could give approval to start pumping. Everything in the
second-level basement was a loss, including equipment for security, heating,
ventilation, air-conditioning, fire sprinkling, and mechanical services. Most
merchandise in the first-level basement stockrooms also was lost.
Electricians
worked around the clock to install emergency generators and restore lighting
and elevator service. Additional security officers were hired. An emergency
pumping system and new piping to the water sprinkling tank were installed so
the sprinkler system could be reactivated. Measures were taken to monitor
ventilation and air quality and dehumidifiers and fans were installed to
improve air quality. Within the week, inspectors from the City of Chicago and OSHA gave
approval to reopen the store.
During
this time, engineers had repaired the hole in the tunnel. After water was
drained from the Marshall Field’s basements, damaged merchandise was removed
and sold to a salvager. The second basement had to be gutted to assure removal
of contaminants. Salvageable machinery had to be disassembled and sanitized.
The
extent of the damage was assessed and insurance claims filed. A construction
company was hired to manage restoration of the damaged areas. Throughout the
ordeal, the public relations department dealt with the media, being candid yet
showing confidence in the recovery effort. Customers had to be assured that the
store was safe and employees kept apprised of the recovery effort.
This
case illustrates crisis management, an important aspect of which is having a
team that moves fast to minimize losses and quickly recover damages. At the
beginning of a disaster there is little time to plan, though companies and
public agencies often have crisis guidelines for responding to emergency
situations. Afterwards they then develop more specific, detailed plans to guide
longer-term recovery efforts.
QUESTIONS
1. In what ways are the
Marshall Field’s flood disaster recovery effort a project? Why are large-scale
disaster response and recovery efforts projects?
2. In what ways do the
characteristics of crisis management as described in this case correspond to
those of project management?
3. Who was (were) the
project manager(s) and what was his or her (their) responsibility? Who was
assigned to the project team and why were they on the team?
4. Comment on the
appropriateness of using disaster recovery efforts such as this.
5. What form of project
management (basic, program, and so on) does this case most closely resemble?
Case 2 Flexible Benefits System
Implementation at Quick Medical Center
The management committee of Quick Medical
Center wanted to reduce
the cost and improve the value and service of its employee benefits coverage.
To accomplish this it decided to procure and implement a new benefits system.
The new system would have no meet four goal; improved responsiveness to
employee needs, added benefits flexibility, better cost management, and greater
coordination of human resource objectives with business strategies. A
multifunctional team of 13 members was formed by selecting representatives of
departments at Quick that would rely most on the new system—Human Resources
(HR), Financial Systems (FS), and Information Services (IS). Representation
from each department was important to assuring all departmental needs would be
met. The team also included six technical experts from the software consulting
firm of Hun and Bar Software (HBS).
Early
in the project a workshop was held with team members from Quick and HBS to
clarify and finalize project objectives and develop a project plan, milestones,
and schedules. Project completion was set at 10 months. In that time HBS had to
develop and supply all hardware and software for the new system; the system had
to be brought on-line, tested, and approved; HR workers had to be trained how
to operate the system and load existing employee data; all Quick employees had
to be educated about and enrolled in the new benefits process; and the
enrollment data had to be entered in the system.
The
director of FS was chosen to oversee the project. She had a technical background
and, prior to serving as director, had worked in the IS group where she
assisted in implementing Quick’s patient care information system. Everyone on
the team approved of her appointment as project leader, and many team members
had worked with her previously. Two team members had worked with her
previously. Two team leaders were also selected, one each from HR and IS. The
HR leader’s task was to ensure that the new system met HR requirements and the
needs of Quick employees, and the IS leader’s task was to ensure that the new
software interfaced with other Quick systems.
Members
of the Quick team were committed to the project on a part-time basis. Roughly
50 percent of the time they worked on the project; the rest of the time they
performed their normal daily duties. The project manager and team leaders also
worked on the project part-time. When conflicts arose, the project took
priority. Given specific performance requirements and time deadlines, the Quick
top management committee made it clear that successful project completion was
imperative. The project manager was given authority over functional managers
and project team members regarding all project related decisions.
QUESTIONS
1. What form of project
management (basic, program, and so on) does this case most closely resemble?
2. The project manager
is also the director of FS, only one of the departments that will be affected
by the new benefits system. Does this seem like a good idea? What are the pros
and cons of her selection?
3. Comment on the team
members’ part time assignment to the project and the expectation that they give
the project top priority.
4. Much of the success
of this project depends on the performance of team members who are not employed
by Quick, namely the HBS consultants. They must develop the entire
hardware/software benefits system. Why was an outside firm likely chosen for
such an important part of the project manager in meeting project goals?
Section - II Solve
any 4 questions
- Explain in detail the phases involved in the Waterfall model.
- A software package is to be designed and build to assist in software cost estimation. It will input certain parameters and produce initial cost estimates to be used at bidding time.
- It has been suggested that a software prototype would be of value in these circumstances. Explain why this might be.
- Discuss how much prototyping could be controlled to ensure that it is conducted in an orderly and affective way and within a specified time span.
- Differentiate between principles of Conventional
Software Engineering and Modern Software Management.
- The application of risk management to software development projects has been strongly advocated. In practice, however, managers are often reluctant to apply the techniques. What do you think might be the reason for this?
- On a large project it is often be the responsibility of a team leader to allocate tasks to individuals. Why might it be unsatisfactory to leave such allocations entirely to the discretion of the team leader?
No comments:
Post a Comment